At this point power appears to be restored to Baldi after ~14 hours on battery.

Thanks all!
Nigel

On Sep 17, 2019, at 21:08, Nigel Vander Houwen <nigel@nigelvh.com> wrote:

FYI,

We remain on batteries at the moment. Earlier this afternoon we shut down a server on site to conserve some power, this was not handling any critical services and no end user impacts are expected. We estimate something on the order of 8 hours more runtime before the batteries are depleted, but that figure could vary as the UPS time estimates really don’t deal with the large battery bank we have very well.

The utility is working on the issue, and I’ve seen updates that other nearby/potentially related issues have been resolved, so hopefully we’ll be back on grid power soon.

Thanks,
Nigel

On Sep 17, 2019, at 18:25, Daniel Stevens via PSDR <psdr@hamwan.org> wrote:

Thank you for the update

Daniel Stevens KL7WM




On Tuesday, September 17, 2019 Nigel Vander Houwen <psdr@hamwan.org> wrote:

Hello All,

Baldi is currently on battery power. The utility is aware of the outage. Currently the site remains at full capability.

Thanks!
Nigel
_______________________________________________
PSDR mailing list
_______________________________________________
PSDR mailing list
PSDR@hamwan.org
http://mail.hamwan.net/mailman/listinfo/psdr

_______________________________________________
PSDR mailing list
PSDR@hamwan.org
http://mail.hamwan.net/mailman/listinfo/psdr